Contract Singing & Colour Selection

Be prepared this is an ALL DAY EVENT !  Lots of Coffee was consumed !

 

 

Date :

"Block Cut and ready to start our build"

Date: Tuesday

Plumbing Prepared

1 day to prepare the plumbing.

 

 

Date:

Foam added and boxed in 2 days.

 

Date :

Concrete Prep

The Retainer wall

Special Thanks to Pete for the help with the wall!

First and second level built in 2 days

Date

Roof installed

Date

Images include Roof and upper level pictures

Internal Plumbing & Electrical Install

Date

Window Installation

Date

The house was wrapped

Date

"One week delay while we wait for brick layers"

Stacker Doors & Windows Installed

Date